Advertisements

Building Project Topics

Effects and Causes of Cost Overrun in Building Construction Projects

Effects and Causes of Cost Overrun in Building Construction Projects

Advertisements

Effects and Causes of Cost Overrun in Building Construction Projects

Chapter One

Objectiveย of theย Study

Generalย Objective

Theย main objectiveย ofย theย studyย is toย identifyย the majorย Causesย ofย Cost Over-runย inย Construction Project:ย Theย caseย ofย Royal Buildings.

Specificย Objective

Theย specificย objectivesย ofย theย studyย includeย theย following:

  • To assess the extent of cost overrun in building construction projects with respect to the project original duration and contract amount.
  • To evaluate the existing problems associated with construction projects completion cost
  • To identify the responsible bodies those, contribute to critical causes of cost over runs
  • Atlast, to forward recommendation about minimization or avoiding cost overrun
  • To identify the internal factors responsible for construction projects cost overrun
  • To identify the external factors responsible for construction projects cost overrun

CHAPTER TWO:

REVIEWย OFย THEย LITERATURE

ย Theoreticalย Review

ย Generalย conceptย ofย costย overrun

Every project is constrained by cost, time and quality, why because almost all projects fail to meet them. Especially the first two are the most important constraint that a project driven companies or anyone who is undertaking a project should give additional attention too, hence delay or increment in one of them cause direct impact on the other. The inability to complete project on time and budget continue to become a chronic problem worldwide (Ahmed et al.2002). The success criteria for projects may differ from one to another but the commons are completing the project with the predefined schedule, with the estimated cost and finally with the requirement defined by the owner. Construction project is mainly undertaken to deliver a product or facility and this industry is growing from time to time here in Nigeria but it faces many problems among those one is cost overrun problems. Construction projects are undertaken considering for the future, it canโ€™t be said that it will be free from uncertaintiesโ€™ so the project may fail due to weather conditions, owners requirement not been met and others like project complexity increases. So this days project been completed with incurring an extra cost. Studies show that in developing countries when the project is completed, the actual cost exceeds the original contract price by 30% (Al-monani, 1996). Cost overrun of 50 to 100% were common (Flyvbjerg et al.,2003). Construction and engineering projects are risky venture: 40% are late; 50 over budget; 30%fail to meet expectations of usersโ€™ (Tony, 2017). There have been many factors identified by many researchers for the cost overrun. There are different stakeholders who are involved in the project mainly client, consultant, contractor, sub- contractor, government and society, and have their own reasons which can be held responsible for project cost overrun. Unfortunately, construction projects regularly are making news headlines, not for being remarkable engineering accomplishments that will support and stimulate economic growth and social integration of communities, but rather for being poorly managed and often over budget. A significant number of construction projects routinely overrun their cost estimates. According to the work of Flyvbjerg et al. (2002), infrastructure projects are reported to have an 86% probability of outrunning their set cost targets. Love et al. (2012) and Odeck (2004) on the other hand found that overruns could be as high as 70% and 183% more than the initial estimates respectively. The global audit and professional services firm, Ernst and Young, reviewed the performance of 365 infrastructure projects delivered in the oil and gas industry and found that at least 64% of the projects were faced cost overruns.

Definitionsย ofย costย overrun Cost overruns

Aย projectย costย isย theย totalย costย thatย theย projectย toย beย implementedย willย incurย untilย itsย finishedย and thisย costย isย estimatedย byย usingย differentย techniques,ย Top-downย orย analogous,ย Bottom-upย and Parametric approach at the project appraisal phase. Project cost overrun occurs when the final costย incurredย isย greaterย thanย theย budgetedย cost.ย Aย costย overrunย alsoย knownย asย costย increaseย or budget overrun, involves unforeseen costs incurred in excess of estimated amount due to an underestimation of the actual cost during budgeting.

Several authors have defined cost overruns differently. For instance, Al-Najjar (2002), has defined cost overruns as the change in contract amount divided by the original contract award amount. However, Zhu and Lin (2004) are of the view that cost overruns are the excess of actual cost over budget and also called it cost increase or budget overrun. Choudhury (2004) have defined cost overruns to be the difference between the original cost estimate of project and actual construction cost on completion of works of a commercial sector construction project. Matty Siemiatycki (2015), the common definition of cost overrun in most studies is a change in cost relative to the final estimate provided when the approval of or โ€œgo decisionโ€ was made until the construction is completed. Widman (2002) defined it the amount by which actual cost exceed the baseline or approved costs.

Advertisements

 

CHAPTER THREE

RESEARCHย METHODOLOGY

ย Introduction

Thisย chapterย outlinesย theย methodย usedย toย conductย thisย research.ย Theย chapterย startsย byย definingย the research approach and research design used for this research. Following thatย the target population forย theย study,ย theย sampleย size,ย samplingย techniquesย areย discussed.ย Furthermore,ย theย dataย source, dataย collectionย methods,ย instruments,ย andย methodsย ofย dataย analysisย areย covered.

Researchย Approach

Researchย approachย isย theย methodologicalย approachย thatย aย researcherย followsย toย understandย and addressย theย statementย ofย theย problem.ย Thereย areย threeย typeย ofย researchย approach:ย qualitative research approach, mixed method research approach and quantitative research approach. The qualitativeย approachย dealย withย multiplicityย ofย realityย andย useย contentย analysis,ย butย quantitative researchย approachย statesย realityย isย singleย andย objective.ย Mixedย researchย approachย employsย both researchย approachesย inย whichย realityย isย contextย basedย andย pragmatism.

This study is a quantitative in nature as it examines the effect of independent variables on dependentย variable.ย Theย findingsย andย conclusionย ofย theย studyย willย dependย onย theย utilizationย of statisticalย dataย collectedย andย analyzedย usingย SPSSย versionย 26.

CHAPTERย FOUR

DATAย PRESENTATION,ย ANALYSIS,ย ANDย INTERPRETATION

Data presentation

This chapter presents the analysis, discussions, and findings on causes of cost overrun in a construction project. This was guided by the objectives toย present empirical evidenceย to agreeย or controvert. The researcher administered questionnaires to collect the data that was analyzed using SPSSย toย beย ableย toย comeย upย withย theย resultsย presentsย here.ย Descriptiveย statisticsย haveย beenย usedย to describe respondentsโ€™ characteristics. The further regression analysis has been used to determineย theย impactย theย independentย variablesย haveย onย theย dependentย variable.ย Theย researcherย issuedย 30 questionnairesย andย hadย aย returnย rateย ofย 30ย orย hundredย percentย (orย 100%)ย responseย rate).

Questionnaire Return rate = 30 X 100/100 = 100%.

CHAPERย FIVE

SUMMARYย OFย FINDINGS,ย CONCLUSIONย AND RECOMMENDATIONS

This chapter is the final chapter which is divided into three sections. The study’s key findings are summarized in the first section, conclusions are presented in the following section, and recommendations are made in the final section based on the findings and conclusions that may apply to the construction sector.

Summaryย ofย Findings

Theย objectiveย ofย thisย studyย wasย toย studyย theย causesย ofย costย over-runย inย aย constructionย projectย ofย the accommodationย andย trainingย centerย constructionย projectย ofย theย KAIZENย instituteย withย aย specificย objectiveย to

  • To assess the extent of cost overrun in building construction projects concerning the project’s original duration and contract
  • To evaluate the existing problems associated with construction project completion
  • Identifying the responsible bodies that, contribute to critical causes of cost
  • To forward recommendations about minimization or avoiding cost overrun

Based on the study objectives, research question, and hypotheses, questionnaires measuring research variables were developed and organized. From the 30 questionnaires distributed, 30 (100%) valid questionnaires were collected and used for analysis. Participants in this study were construction site professionals. Project managers, civil engineers, accountants, and others with organizational experience from less than 1 year to 15 years were the professionals who participated in completing the questionnaire. The collected data were analyzed using the Social Science Software (SPSS) statistical package. A simple regression analysis was used to test the hypothesis.

Descriptiveย analyzesย wereย calculatedย andย presentedย inย theย table.ย beforeย applyingย theย regression

Assumption tests such as analysis, linearity, and normal distribution were performed. We analyzed respondents’ opinions on prevalence, causes, and effects using descriptive statistics such as frequency, percent mean, and standard deviation, and ranked them using the Relative Importance Index (RII). Based on descriptive statistical analysis, most respondents agree that the problem exists and occurs frequently at the Royal Buildings.

Based on data obtained from the descriptive analysis, the most important causes and effects of cost overruns are ranked using the Relative Importance Index (RII), and the most frequently assessed causes of cost overruns areย poorย contractย managementย andย examinedย itsย impact.ย Afterย testingย allย assumptions,ย aย regressionย analysisย of project cost overruns wasย performed and found that cost overruns have a significant impactย on project performanceย withย R2 = 0.787, Fโ€“ratio = 16.62 & sig= 0.004 < 0.05, and p-value < 0.01. Finally, based on the results of the ANOVA table the alternative hypothesis was accepted.

ย Conclusions

Cost overruns have the adverse effect of impacting the financial viability of the project. The problem of cost overruns is exasperated when the necessary funding to cover increased costs cannot be arranged promptly. Delays in arranging the funding necessary to cover cost overruns will only increase costs further, which can get the project into trouble and eventually cause the project to end and never a start.

The objectives of the study have been successfully identified. Most of the factors that cause cost overrun were identified, among these factors most important factors that contributed to the cause of cost overrun include poor contract management, the procurement process being ambiguous and without planning, lack of timely decision and corrective actions, Slow response from the management of the project, the complexity of the project, escalation of materials price and inflation in the cost of construction materials, escalation of exchange rate and inadequate experience staff and poor labor productivity within the project team are the main cause of the project cost overrun. As the regression analysis showed there is a strong, positive, and significant relation between the cause of the cost overrun and project cost.

Recommendations

Alignedย withย the aboveย conclusion,ย theย researcherย proposesย the followingย recommendations that shouldย be consideredย byย theย institute

  • There are factors which can be controlled and improved by the company however, there are also factors which are beyond the control of the contractor like currency exchange, economic instability, transportation cost, labor cost, delay in progress payment, incremental price of materials and complexity of the construction project.
  • Efficient contract management, site management, and inspection should be developed.
  • The procurement process should be done properly and with the appropriate planning
  • The responsible parties must estimate costs realistically because increment is a reality of life in the modern world.
  • Carrying out identifications of factors for cause of cost overrun and then identifying the significance and importance of each of the identified the most sever cause prior to planning to address these causes for effectiveness.
  • Escalation in material price should be considered during planning and
  • The recruitment of the employees needs to do with the proper qualification and the selection process has to be done with
  • The project managers have to give timely and appropriate decisions regarding the matters which occurred during the
  • The project manager must keep up to date with today’s life and manage the projects

Based on Ibbs et al. (2001) suggestion of having a systematic approach to managing project change, it is advised to have a balanced change culture, recognize the change before its occurrence, evaluate the change, and implement approved change with continuous improvements.

REFERENCES

  • A Guide to the Project Management Body of Knowledge (2000). Project Management Institute. Newtownย Square,ย Pennsylvaniaย USA.
  • A Guide to the Project Management Body of Knowledge (2000). Project Management Institute. Newtownย Square,ย Pennsylvaniaย USA.
  • Abdul Rahman. H., (1993) The management and Cost of quality for civil engineering projects. PhDย Thesis, University ofย Manchester Institute ofย Scienceย &ย Technol
  • Ashebirย S.B,ย Wubishetย J.,ย Muradย M.ย (2017).ย Causesย ofย Costย Overrunย inย Federalย Roadย Projects ofย Nigeriaย inย Caseย ofย Southernย District.ย Americanย Journalย ofย Civilย Engineering.ย Vol.ย 5, No. 1, 2017, pp. 27-40.
  • Biruktawitย Tesfayeย (2018)ย Assessmentย ofย Projectย cost overrun, Its cause andย Theย Mitigation Measures
  • Cantarelliย C.,ย Chousย C.ย &ย Cunnighamย S.Wย (2013).ย Explainingย Costย Overrunsย ofย LargeScale Transportation Infrastructureย Projects using aย Signaling Gam
  • Charlesย T.H.,ย Srikantย M.ย D.,ย Georgeย F.ย (2003).ย Costย accountingย managerialย emphasis:ย 11th edition, Prentice โ€“ Hall of India, New Delhi
  • Cox,ย A.ย &ย Thompson,ย I.ย (1997)ย ‘Fitย forย Purposeย Contractualย Relations:ย Determiningย a Theoreticalย Frameworkย forย Constructionย Projects’.ย Europeanย Journalย ofย Purchasingย & Supplyย Management,ย 3ย (3),ย 127-135.
  • Ejazย N.,ย Aliย I.,ย &ย Tahirย M.F.ย (2010).ย Assessmentย ofย delaysย andย costย overrunsย during constructionย projectsย inย Pakistan.
WeCreativez WhatsApp Support
Our customer support team is here to answer your questions. Ask us anything!