Building Project Topics

Impact of Mismanagement of Material on Initial Cost of a Building Project

Impact of Mismanagement of Material on Initial Cost of a Building Project

Impact of Mismanagement of Material on Initial Cost of a Building Project

CHAPTER ONE

Objectives of the study

The main objective of the study is to examine the impact of mismanagement of material on initial cost of a building project in Uyo LGA.

Specifically, the study sought to:

  1. Examine the material mismanagement level at various stages of construction on site.
  2. Examine the factors contributing to material mismanagement on construction sites.
  3. Examine the effectiveness of methods for minimization of material mismanagement on site.

CHAPTER TWO

LITERATURE REVIEW

Definition of Construction Waste

Researchers and authors have different views as to what constitutes construction waste and provided various definitions in relevant literature. Cheung, (2016) defines construction waste as the by-product generated and removed from construction, renovation and demolition workplaces or sites of building and civil engineering structures. As Shen et al, (2021) defines it is the difference between the value of materials delivered and accepted on site and those properly used as specified and accurately measured in the work, after deducting the cost savings of substituted materials transferred elsewhere, in which unnecessary cost and time may be incurred by material mismanagements.

The wider definitions of construction waste include the concept of value. According to Formoso et al, (2016), for instance, ‘waste is defined … as the loss of any kind of resources— materials, time (labor and equipment), and capital—produced by activities that generate direct or indirect costs but do not add any value to the final product from the point of view of the client’.

Skoyles (2021) defines waste broadly as the difference between the value of materials delivered and accepted on site and those properly used as specified and accurately measured in the work after deducting the cost saving of substituted materials transferred elsewhere, in which unnecessary cost and time may be incurred by materials mismanagement. His definition includes and indirect waste  due to substitution or inefficiency as well as  monetary loss such as, waste due to concrete slab thickness larger than specified by the structural designs.

Shen,et al (2016 ) also defined construction waste broadly as the difference between the value of materials delivered and accepted on site and those properly used as specified and accurately measured in the work after deducting the cost saving of substituted materials transferred elsewhere in which unnecessary cost and time may be increased by the material mismanagement.

Serpell and Alarcon (2018) presented a similar concept stating that all construction activities that produce direct or indirect cost, but do not add value or process to the product can be called waste. Construction waste is also considered as losses resulting from activities that consume direct or indirect costs but do not add value to the product.

This study focuses on direct material waste produced during the construction process and lifecycle of the study sides and excludes indirect waste such as those relating to manufacturing, production and transport.

 

CHAPTER THREE

MATERIALS AND METHODS

Research design

The study employed quantitative descriptive research design to examine the impact of mismanagement of material on initial cost of a building project in Uyo LGA. The scope of this research work will cover the collection of data from all the organizational hierarchy and levels of management of the company. To achieve this, the researcher would adopt good methods of data collection, analysis and interpretation of the research through the use of chi-square.

Sources of Data

The data for this study were generated from two main sources; Primary sources and secondary sources. The primary sources include questionnaire, interviews and observation. The secondary sources include journals, bulletins, textbooks and the internet.

CHAPTER FOUR

DATA PRESENTATION AND ANALYSIS

Information gathered from interviews conducted and questionnaires administered to respondents were converted to data expressed in percentages as presented in Table 4.1. The data were tabulated according to the response of the question answered with the use of yes or no options as required by variables.

CHAPTER FIVE

SUMMARY OF FINDINGS, CONCLUSION AND RECOMMENDATIONS

Summary of findings

In the course of this study, certain findings were made and necessary recommendations were also made as follows:

  1. In hypothesis 1, based on the decision rule, the null hypothesis (Ho) was rejected and the alternative hypothesis (Ha) accepted. Thus, it was concluded that material mismanagement is not totally avoidable on construction site.
  2. In hypothesis 2, the null hypothesis (Ho) was accepted and it was concluded that mismanagement results from human error rather than being inherent in process or methods.
  3. After the analyses of the ranking of factors responsible for material mismanagement on construction site, the following factors were discovered to contribute to material mismanagement on construction site in the under listed order:
  4. Poor Supervision = 80%
  5. Attitude of worker = 72%
  6. Inexperience               = 71%
  7. Inefficiency    = 64%
  8. Vandalism   = 62%
  9. Poor workmanship = 64%
  10. Theft        = 60%

From the above ranking, it was established that the major cause of material mismanagement on construction sites is the attitude of workers to their various jobs. This arises from the facts that most workers do not appreciate the work they found themselves doing. It ultimately results in a nonchalant attitude to work and this affects the way they handle materials on construction sites.

Based on the observation made during the course of this study, the following can be attributed to the level of material mismanagement on construction sites. On most sites, there was poor supervision giving room to most workers to work as they please on site. Example; already mixed mortar was left without placing for more than two hours by workers who claimed that they went for break. Also, there was inadequate or lack of good storage facilities on some site. It was equally observed that there was lack of proper security arrangement, therefore cases of theft were reported which could have been perpetrated by site workers or other persons.

Conclusion

The study identified that material mismanagement is not totally avoidable on site. Material mismanagement results from human error rather than being inherent in the process or methods. Sandcrete blocks are more prone to mismanagement due to their susceptibility to breakage during handling and transit as workers do not carefully stack blocks properly on site or sometimes stack them too high. Poor Supervision was also ranked as high factor that causes material mismanagement on construction sites; it is therefore concluded that competent staff (Supervisors) should be employed to supervise construction projects to enforce strict rules that will enhance minimization of material mismanagement.

Recommendations

Based on the findings of this study, the following have been put forward as recommendations:

  1. Monetary incentives should be introduced so that workers get motivated and thereby change their negative attitude to work.
  2. There is need for workers to exercise more care when carrying out their work especially while working with breakable materials such as sandcrete blocks, tiles, ceiling boards etc.
  3. Competent staff (Supervisors) should be employed and allocated to construction sites to enforce strict rules that will enhance minimization of material mismanagement.
  4. Adequate security should be provided for construction materials on site.
  5. There is need to ensure that materials delivered to sites are those specified and ordered for.
  6. There should be awareness programmes for all construction companies on construction waste management. Formal education should be given to storekeepers and foremen on effective material handling system.
  7. Finally, the use of computers for storing records on construction sites should be encouraged.

REFERENCES

  • Adejuwon, J. O. (2015). Rainfall Seasonality in the Niger Delta Belt, Nigeria. Journal of Geography and Regional Planning, 5(2): 51-60.
  • Adewuyi, T. O. (2015). Construction Material Waste Planning and Control Techniques on Building Sites in South-South of Nigeria (Unpublished PhD Thesis). Department of Building, Faculty of Environmental Studies, University of Uyo, Uyo, Nigeria.
  • Adewuyi, T.O. Idoro, G.I. & Ikpo, I.J. (2018). Empirical Evaluation of Construction Material Waste Generated on Sites in Nigeria. Civil Engineering Dimension, 16(2): 96-103.
  • Akanni, P.O. (2017). An Empirical Survey of the Effect of Materials Mismanagement on Contractors’ Profit Level in Construction Projects.  The Professional Builders: Journal of the Nigerian Institute of Building, 35–46.
  • Akinkurolere, O.O. & Franklin, S.O. (2015). Investigation into Waste Management on Construction Sites in South Western Nigeria. American Journal of Applied Sciences, 2 (5): 980 – 984.
  • Al-Moghany, S. S. (2016). Managing and Minimizing Construction Waste for Gaza Strip (Unpublished Master’s Thesis). Faculty of Engineering, Deanery of Graduate Studies, Construction Management Programme, The Islamic University of Gaza, Gaza, Palestine.
  • Alwi, S., Hampson, K. & Mohamed, S. (2021). Waste in the Indonesian Construction Projects. Proceeding of CIB W107 1st International Conference: Creating a Sustainable Construction Industry in Developing Countries, 11 to 13 November, Stellenbosch, South Africa, 305-315.
  • Berg, R. & Hinze, J. (2015). Theft and Vandalism on Construction Sites.  Journal of Construction Engineering and Management, 131 (7): 826-833.
  • Bossink, B.A.G. & Brouwers, H.J.H. (2016). Construction Waste: Quantification and Source Evaluation. Journal of Construction Engineering and Management, 122 (1): 55-60.
  • Dania, A.A., Kehinde, J.O., & Bala, K. (2017). A Study of Construction Material Waste Management Practices by Construction Firms in Nigeria. Proceedings of the 3rd Scottish Conference for Postgraduate Researchers of the Built and Natural Environment, Glasgow, 121-129.
  • Ekanayake, L. L. & Ofori, G., (2020). Construction Material Waste Source Evaluation. Proceedings of the 2nd Southern African Conference on Sustainable Development in the Built Environment, Pretoria, South Africa, 1-6.
WeCreativez WhatsApp Support
Our customer support team is here to answer your questions. Ask us anything!